Full-length construction + project management resumes from commercial + multifamily GC to owner's-rep + capex. Each leads with project value + schedule + safety, names subcontractor + code + LEED work, and surfaces the delivery signals owners + developers grade on.

ByTomás Albrecht·Senior Resume Writer·Reviewed byDaniel Ortega· Head of Writing·1 example

Construction manager hiring grades on three axes: project scope (type, value, schedule, delivery model), delivery discipline (safety, schedule, cost, quality, code), and team + coordination (subs, self-perform, design team, AHJ, owner). CM resumes are 1-2 pages.

For superintendent-track candidates, lead with self-perform trades + on-site coordination + safety record. For PM / senior PM candidates, lead with GMP + schedule + CO management + owner coordination. For CM-at-risk / owner's-rep candidates, surface preconstruction + estimating + design coordination.

The example

Rafael Ostrowski-Bencomo

Sr PM · $148M Mixed-Use · 28mo On Time · TRIR 0.6 · LEED AP · Turner Alum
Brooklyn·US·[email protected]·+1 (718) 555-0384·linkedin.com/in/rafael-ostrowski

Summary

Senior Project Manager (CM-at-risk delivery); currently on a $148M ground-up 22-story mixed-use tower (200 residential + 8 retail + 4-level below-grade parking); 28-month schedule tracking on time + $2.4M under $148M GMP; TRIR 0.6 (ENR industry avg 2.1); OSHA 30 + LEED AP BD+C + PMP. 10 yrs across Turner + Suffolk + current firm.

Experience

Senior Project Manager — Mixed-Use Tower
Structure Tone (CM-at-risk delivery) · Brooklyn, NY
Aug 2024Present
  • Project scope: 22-story ground-up mixed-use ($148M GMP, 288k sqft, 200 residential + 8 retail + 4-level below-grade parking); 4 tier-1 self-perform trades + 38 subcontractors; Procore + Bluebeam + P6 primary.
  • Schedule: 28-month baseline with 3-week float; currently 4 days ahead of critical path (P6 + 4-week lookahead); recovered 12 days after Q2 concrete supplier disruption via re-sequenced pour + parallel MEP rough-in.
  • Cost: $2.4M under $148M GMP; change-order log 1.4% of contract (industry benchmark 4-6%); 14 approved COs (all owner-directed + 0 subcontractor-back-charge).
  • Safety: TRIR 0.6 (ENR industry avg 2.1) + DART 0.4 + zero-LTI 22 months + weekly toolbox talks + monthly OSHA-walk with 4 trade foremen; 148k combined labor hours without a recordable event.
  • Code + AHJ: NYC DOB + FDNY coordination weekly; 22 special inspections per IBC 1704; TCO strategy for phased occupancy across 4 residential floors; 62 milestone inspections passed without re-inspection.
Project Manager
Suffolk Construction · New York, NY
Jun 2020Jul 2024
  • PM on $84M hospital MOB (2018-2020, LEED Silver) + $62M academic renovation (2020-2022).
  • Both projects delivered under GMP; TRIR < 1.0 across tenure.
Assistant PM → PM
Turner Construction · New York, NY
Jun 2016May 2020
  • APM → PM at Turner; worked on $62M mid-rise multifamily (2016-2018) + $28M Fortune 100 HQ fit-out (2014-2016).
  • Turner Green Belt (Lean Construction, 2017).

Credentials

PMP — Project Management Professional
PMI·Apr 2022
LEED AP BD+C
USGBC / GBCI·Aug 2021
OSHA 30 Hour Construction + STS-C (renewed 2026)
OSHA + BCSP·Jan 2026
First Aid + CPR + Confined Space + Scaffold Competent Person (current)
Red Cross + NYC DOB·Feb 2026

Education

BS in Construction Management
Polytechnic Institute of NYU (now NYU Tandon)
Aug 2012May 2016
senior

Senior CM (CM-at-Risk, Commercial)

Sr PM · $148M mixed-use · 28mo on time · TRIR 0.6 · LEED AP · Turner alum

Use this template

Live preview · Senior CM (CM-at-Risk, Commercial)

Use this resume

Why this resume works

Header names project + $ + schedule + safety + credential + firm. Bullets quantify project + trades + safety + cost + LEED.

Rafael Ostrowski-Bencomo

Sr PM · $148M Mixed-Use · 28mo On Time · TRIR 0.6 · LEED AP · Turner Alum
Brooklyn·US·[email protected]·+1 (718) 555-0384·linkedin.com/in/rafael-ostrowski

Summary

Senior Project Manager (CM-at-risk delivery); currently on a $148M ground-up 22-story mixed-use tower (200 residential + 8 retail + 4-level below-grade parking); 28-month schedule tracking on time + $2.4M under $148M GMP; TRIR 0.6 (ENR industry avg 2.1); OSHA 30 + LEED AP BD+C + PMP. 10 yrs across Turner + Suffolk + current firm.

Experience

Senior Project Manager — Mixed-Use Tower
Structure Tone (CM-at-risk delivery) · Brooklyn, NY
Aug 2024Present
  • Project scope: 22-story ground-up mixed-use ($148M GMP, 288k sqft, 200 residential + 8 retail + 4-level below-grade parking); 4 tier-1 self-perform trades + 38 subcontractors; Procore + Bluebeam + P6 primary.
  • Schedule: 28-month baseline with 3-week float; currently 4 days ahead of critical path (P6 + 4-week lookahead); recovered 12 days after Q2 concrete supplier disruption via re-sequenced pour + parallel MEP rough-in.
  • Cost: $2.4M under $148M GMP; change-order log 1.4% of contract (industry benchmark 4-6%); 14 approved COs (all owner-directed + 0 subcontractor-back-charge).
  • Safety: TRIR 0.6 (ENR industry avg 2.1) + DART 0.4 + zero-LTI 22 months + weekly toolbox talks + monthly OSHA-walk with 4 trade foremen; 148k combined labor hours without a recordable event.
  • Code + AHJ: NYC DOB + FDNY coordination weekly; 22 special inspections per IBC 1704; TCO strategy for phased occupancy across 4 residential floors; 62 milestone inspections passed without re-inspection.
Project Manager
Suffolk Construction · New York, NY
Jun 2020Jul 2024
  • PM on $84M hospital MOB (2018-2020, LEED Silver) + $62M academic renovation (2020-2022).
  • Both projects delivered under GMP; TRIR < 1.0 across tenure.
Assistant PM → PM
Turner Construction · New York, NY
Jun 2016May 2020
  • APM → PM at Turner; worked on $62M mid-rise multifamily (2016-2018) + $28M Fortune 100 HQ fit-out (2014-2016).
  • Turner Green Belt (Lean Construction, 2017).

Credentials

PMP — Project Management Professional
PMI·Apr 2022
LEED AP BD+C
USGBC / GBCI·Aug 2021
OSHA 30 Hour Construction + STS-C (renewed 2026)
OSHA + BCSP·Jan 2026
First Aid + CPR + Confined Space + Scaffold Competent Person (current)
Red Cross + NYC DOB·Feb 2026

Education

BS in Construction Management
Polytechnic Institute of NYU (now NYU Tandon)
Aug 2012May 2016

What hiring managers look for

The specific signals an experienced construction manager hiring panel grades on during the eight-second scan.

  • Project type + value + schedule

    'PM on a $148M mixed-use ground-up; 28-month schedule' beats 'construction manager.'

  • Safety record

    OSHA recordable + DART + TRIR + zero-LTI.

  • Subcontractor + trades scope

    Trades + subs + tier-1 self-perform + procurement.

  • Code + inspections

    IBC + local amendments + DOB + FDNY + special inspections.

  • Delivery model

    GC vs CM-at-risk vs design-build vs owner's rep.

  • LEED + sustainability + commissioning

    LEED accreditation + commissioning + energy code.

How to write a construction manager resume

  1. 1

    Open with project + value + schedule

    Project + $ + schedule + delivery + role.

  2. 2

    Quantify safety + schedule + cost

    TRIR + DART + $ + CO % + on-time.

  3. 3

    Surface trades + subs + procurement

    Self-perform + subs + bid + $ + CSI.

  4. 4

    Name code + AHJ work

    IBC + local + special inspections + AHJ.

  5. 5

    Close with credentials + firms

    OSHA + LEED + PMP + Turner / Suffolk / Skanska.

Pro tip

Lead with project value + schedule + safety

'$148M mixed-use, 28-month schedule, on time + $2.4M under GMP, TRIR 0.6' is the CM signal.

Pro tip

Schedule discipline > handshakes

MS Project / Procore schedule + lookahead + recovery + critical path.

Pro tip

Safety compounds

OSHA 30 + STS-C + STSC + STP + LEED APs each = tier.

Pro tip

Delivery model matters

GC / CM-at-risk / design-build / owner's rep — distinct hiring tracks.

ATS notes

CM ATS pipelines screen for delivery + software + credential tokens. Delivery models: GC (General Contractor), CM-at-risk, CM-agency, design-build, EPC, IPD (Integrated Project Delivery), owner's rep. Software: Procore, Autodesk Construction Cloud (BIM 360), Bluebeam Revu, Primavera P6, MS Project, Sage 300 CRE (Timberline), Viewpoint Vista, Textura, Buildertrend, PlanGrid, Fieldwire. BIM: Revit, Navisworks, Tekla. Estimating: On-Screen Takeoff (OST), Bluebeam, HeavyBid, Sage Estimating, ProEst. Code: IBC + IRC + IPC + IMC + IECC + NEC + IFC + ADA + local amendments. Special inspections: 1704 (NYC DOB), Type III + Type V per IBC. Certifications: OSHA 30 Hour Construction, STS-C (Safety Trained Supervisor Construction), STSC + STP, PMP, LEED AP BD+C + O+M + ND, CCM (Certified Construction Manager), DBIA (Design-Build Institute of America), AGC / ABC training programs. Firms: Turner, Skanska, Suffolk, Gilbane, Hensel Phelps, Whiting-Turner, DPR, McCarthy, Clark, Structure Tone, Tishman.

Sample bullets you can adapt

Each follows the [verb] [object] [number] structure hiring managers grade against. Copy them as a starting point, swap in your own numbers, and read the annotation to understand why each one works.

  • Scope

    Project scope FY24: 22-story mixed-use ($148M GMP, 288k sqft, 200 residential + 8 retail + 4-level below-grade parking); 4 tier-1 self-perform trades + 38 subcontractors; Procore + Bluebeam + P6 primary.

    Why it works: $ + sqft + program + trades + tools.

  • Schedule

    Schedule: 28-month baseline with 3-week float; currently 4 days ahead of critical path (P6 + 4-week lookahead); recovered 12 days after Q2 concrete supplier disruption via re-sequenced pour + parallel MEP rough-in.

    Why it works: Baseline + float + recovery detail.

  • Cost

    Cost: $2.4M under $148M GMP; change-order log 1.4% of contract (industry benchmark 4-6%); 14 approved COs (all owner-directed + 0 subcontractor-back-charge).

    Why it works: $ + CO % + composition.

  • Safety

    Safety: TRIR 0.6 (ENR industry avg 2.1) + DART 0.4 + zero-LTI 22 months + weekly toolbox talks + monthly OSHA-walk with 4 trade foremen; 148k combined labor hours without a recordable event.

    Why it works: TRIR + DART + labor-hours + cadence.

  • Subs

    Subcontractor + procurement: bid + awarded 38 subcontracts across 24 CSI divisions ($112M combined); managed 4 self-perform trades in-house ($36M); weekly sub-progress meetings with 4 lead superintendents.

    Why it works: Bid count + $ + CSI + cadence.

  • Code

    Code + AHJ: NYC DOB + FDNY coordination weekly; managed 22 special inspections per IBC 1704; TCO strategy for phased occupancy across 4 residential floors; passed 62 milestone inspections without re-inspection.

    Why it works: AHJ + IBC + phased TCO + inspection outcomes.

  • LEED

    LEED + sustainability: pursuing LEED Gold BD+C v4; managed 4 commissioning agents + shipped Systems Manual + M&V plan; expected 22% energy-cost reduction vs ASHRAE 90.1 baseline.

    Why it works: LEED + commissioning + M&V + energy delta.

  • Precon

    Preconstruction: led 6-month precon for the tower (estimating 3 iterations + value engineering saved $4.8M pre-award); coordinated with design team on 4 RFIs / week during CD phase.

    Why it works: Precon + VE $ + RFI cadence.

  • Team

    Team + supervisory: 4 direct-report Assistant PMs + 2 project engineers + 8 field superintendents (across trades); mentored 2 APMs through PM promotion in 2024.

    Why it works: Direct reports + roles + promotions.

  • Prior

    Prior projects: $84M hospital MOB (Suffolk, 2018-2020, LEED Silver); $62M mid-rise multifamily (Turner, 2016-2018); $28M interior fit-out for a Fortune 100 HQ (Turner, 2014-2016).

    Why it works: 3 projects + $ + firms + type.

  • Credentials

    Credentials: OSHA 30 (renewed 2024) + STS-C + LEED AP BD+C + PMP + First Aid / CPR + Confined Space + Scaffold Competent Person; DBIA candidate.

    Why it works: 6 credentials + pursuit.

  • Arc

    Career arc: Turner 2014-2018 (PE → APM) → Suffolk 2018-2022 (PM, 2 healthcare projects) → current firm 2022 (Sr PM, ground-up mixed-use).

    Why it works: Firms + roles + project types.

Wrong vs Right · bullet rewrites

Same intent, two phrasings. Read why the right column lands on the keep-pile and the wrong column doesn't.

Summary

Wrong

Experienced construction manager.

Right

Senior Project Manager (CM-at-risk delivery); currently on a $148M ground-up 22-story mixed-use tower (200 residential + 8 retail + 4-level below-grade parking); 28-month schedule tracking on time + $2.4M under $148M GMP; TRIR 0.6 (ENR industry avg 2.1); OSHA 30 + LEED AP BD+C + PMP. Prior 8 yrs at Turner + Suffolk.

Why: Role + delivery + project + schedule + budget + safety + credentials + firms.

Project scope

Wrong

Managed large construction projects.

Right

Project scope FY24: 22-story mixed-use ($148M GMP, 288k sqft); 4 tier-1 self-perform trades (concrete, framing, drywall, MEP-rough) + 38 subcontractors; Procore + Bluebeam + P6 schedule primary; owner + design team + AHJ coordination weekly.

Why: Storeys + $ + sqft + trades + subs + tools + coordination.

Safety + record

Wrong

Focused on safety.

Right

Safety record: TRIR 0.6 (ENR industry avg 2.1) + DART 0.4 + zero-LTI 22 months + weekly toolbox talks + monthly OSHA-walk with 4 trade foremen; 148k combined labor hours without a recordable event.

Why: TRIR + DART + duration + cadence + labor-hours.

Schedule + cost

Wrong

Delivered on time and budget.

Right

Schedule: 28-month baseline with 3-week float; currently tracking 4 days ahead of critical path (P6 + 4-week lookahead); recovered 12 days after a Q2 concrete supplier disruption via re-sequenced pour + parallel MEP rough-in. Cost: $2.4M under GMP + change-order log 1.4% of contract (industry benchmark 4-6%).

Why: Baseline + float + recovery detail + $ + CO %.

Trades + procurement

Wrong

Coordinated subcontractors.

Right

Subcontractor + procurement: bid + awarded 38 subcontracts across 24 CSI divisions ($112M combined); managed 4 tier-1 self-perform trades in-house (Turner concrete + framing + drywall + MEP-rough, $36M combined); weekly sub-progress meetings with 4 lead superintendents.

Why: Bid count + divisions + $ + self-perform + cadence.

Skip the blank page

Start from the senior cm (cm-at-risk, commercial) example

Edit the names, the numbers, the company — yours in under a minute.

Use this template

Common mistakes (and how to fix them)

Patterns our writers see most often when reviewing construction manager resumes — each one disqualifies candidates faster than weak experience does.

  • Mistake

    Generic 'construction management.'

    Fix

    Project + $ + schedule + safety + delivery.

  • Mistake

    No TRIR / DART.

    Fix

    Named safety metrics vs industry benchmark.

  • Mistake

    Schedule without recovery detail.

    Fix

    Baseline + float + recovery.

  • Mistake

    CO log missing.

    Fix

    $ + CO % + composition.

  • Mistake

    Subs vague.

    Fix

    Bid + CSI + $ + cadence.

  • Mistake

    Two-page + fluff.

    Fix

    1-2 pages, project-dense.

  • Mistake

    Missing LEED / commissioning.

    Fix

    LEED tier + commissioning + energy delta.

  • Mistake

    Precon buried.

    Fix

    Estimating + VE + RFI.

Resume format for Construction Managers

Reverse-chronological. Header → project + $ + schedule + safety + credentials summary → experience (with schedule + cost + safety + subs + code detail) → prior projects → credentials + firms. 1-2 pages.

Salary & job outlook

Median annual salary

$104,900 (senior PM at Turner / Suffolk / Skanska $140-220k; VP / Ops Mgr $180-320k)

Range: $62,910 to $172,610+

Projected job growth

+9% from 2023 to 2033 (faster than average)

Action verbs for construction managers

Strong verbs lead strong bullets. Replace generic openers (worked on, helped with, was responsible for) with the specific verb that matches what you actually did.

PM'dGMP-managedTRIR-heldscheduled (P6)recovered (schedule)value-engineeredLEED-ledcommissionedAHJ-coordinatedTCO-phasedself-performedbid + awardedCO-negotiatedsafety-walkedAPM-mentoredTurner-tenured

Skills hiring managers screen for

ATS pipelines weight your Skills section as a structured list. Include 15-25 of the items below if they match your experience — not soft skills.

GC + CM-at-risk + CM-agency + design-build deliveryProcore + Autodesk Construction Cloud (BIM 360)Bluebeam Revu + PlanGrid + FieldwirePrimavera P6 + MS Project + Asta PowerprojectSage 300 CRE (Timberline) + Viewpoint VistaOnScreenTakeoff + Sage Estimating + ProEstRevit + Navisworks + Tekla (BIM coordination)IBC + IRC + IPC + IMC + IECC + NEC (code fluency)IBC 1704 special inspections + AHJ coordinationLEED AP BD+C + O+M + NDOSHA 30 + STS-C + STSC + STPPMP + CCM + DBIA + AGC trainingCSI MasterFormat 50-division fluencyEstimating + value engineering + constructabilityChange-order + RFI management + submittal log disciplinePunch list + TCO + closeout + as-built + O&MPreconstruction + owner + design team coordinationOwner's rep + capex reporting

FAQ

How important is TRIR / DART?+

Critical. ENR benchmark is 2.1 TRIR. Below 1.0 is top decile.

Should I list every project?+

Lead with 2-3 recent + list 3-4 prior with $ + type + firm.

GC vs CM-at-risk vs owner's rep framing?+

Distinct hiring tracks. Specialize + surface delivery model at each project.

How important is LEED?+

Increasingly. LEED AP + shipped LEED-certified project = differentiator.

Should I include field superintendent tenure?+

Yes if you have it. Self-perform + trade coordination signals credibility.

P6 vs MS Project?+

P6 for larger commercial + infrastructure. MS Project for smaller + tenant fit-out.

How important is Procore?+

Table-stakes in commercial. Tenure + module familiarity signal.

Do I need a degree?+

BS in Construction Management + Civil Engineering common at senior. Alternative paths via AGC + CCM.

Union vs non-union framing?+

Regional. NYC + Chicago + Boston union-heavy — surface labor-relations experience.

Should I mention safety incidents?+

Zero-recordable + labor-hours milestones are strong signals. Don't hide history — frame recovery.